Installing a mezzanine goods lift is often one of the most practical ways to make full use of warehouse space. When specified correctly, it provides a safe and efficient method of transferring materials between floors without relying on manual handling or sacrificing valuable floor area.
This case study explains how Scissor Tables UK supplied and installed a 500kg mezzanine goods lift for Allaero’s new warehouse, creating a reliable method of moving air parts and aircraft batteries to an upper mezzanine floor. It also provides practical guidance for warehouse managers, facilities teams and operations directors researching mezzanine goods lifts and goods lifts for warehouse mezzanine floors.
Allaero built a new warehouse to support the storage and production of air parts and batteries. As part of that project, the business needed a safe, space-efficient way to move goods from ground floor level to a new upper mezzanine floor.
In his initial enquiry, Paul Greasley, Director at Allaero, set out the requirement clearly:
“We have a requirement for a Mezzanine lift to be installed in a new-build warehouse.” He also explained the expected duty: “We don’t anticipate it being used more than 5-6 times a day, with a total lift weight being no more than 500kg.”
That early clarity mattered. This was not a high-cycle logistics application. It was a practical warehouse requirement where loads needed to be transferred safely and consistently to mezzanine level without overcomplicating the building layout.
The intended load type was also important. Allaero wanted to move airparts and aircraft batteries to the upper floor by wheeling scissor lift tables carrying batteries into the lift. That meant the lift needed to do more than simply lift 500kg. It needed to provide a straightforward, predictable interface for wheeled loading and unloading.
The final solution was a 500kg mezzanine goods-only lift with a 1350mm x 1350mm usable platform, 90-degree loading arrangement, full cladding enclosure, twin interlocked gates at ground and first floor and one-touch automatic controls. Bridging plates were included at both levels, removing the need for a permanent ramp.
A mezzanine goods lift is a goods-only lifting platform designed to move materials safely between ground floor and mezzanine level inside a building. It is commonly used where manual handling would be inefficient or unsafe, but a passenger lift would be unnecessary or unsuitable.
Mezzanine Goods Lifts are often used in:
Warehouses and distribution units
Manufacturing and assembly areas
Parts storage facilities
Trade counters and stockrooms
New-build industrial buildings with mezzanine floors
They are particularly suitable where:
Loads are heavy, awkward or repetitive to move manually
Goods are transferred on trolleys, pallet trucks, cages or wheeled equipment
Travel is between two defined levels
Forklift trucks cannot safely access the mezzanine level or would introduce unnecessary risk inside the building
Floor space is valuable and long ramps are undesirable
The lift is for goods use only, operated by trained personnel
In Allaero’s case, a mezzanine goods lift was the right solution because it allowed the upper floor to become genuinely usable for storage and production, without relying on improvised handling methods or sacrificing valuable floor area to a large ramped approach.
A mezzanine floor adds usable square footage, but only if goods can be moved between levels safely and efficiently. In Allaero’s case, a mezzanine goods lift was required to provide a defined and repeatable transfer method for air parts and aircraft batteries, rather than relying on manual handling or temporary workarounds.
This was one of the most important considerations on the project. Paul Greasley raised it directly: “Space is at a premium in the new building, so to have chunks of it lost to a ramp is not desirable.”
The warehouse loading pattern also introduced an additional constraint. The lift tables carrying batteries were brought into the building through a nearby personnel door, meaning a ramp at the lower level would have obstructed access and made manoeuvring difficult.
To maintain a clear access route and avoid losing valuable floor space, the mezzanine goods lift was specified as a pit-mounted installation, allowing wheeled equipment to move directly onto the platform at floor level.
Because Allaero planned to load the lift using scissor lift tables carrying aircraft batteries, the platform access needed to be practical for wheeled equipment. The transition between the warehouse floor and the lift platform had to be smooth and predictable, allowing operators to move loads safely without awkward manoeuvring.
A pit-mounted mezzanine goods lift ensured the platform sat flush with the warehouse floor, providing straightforward loading for wheeled lift tables.
With expected use of only 5–6 times per day, the requirement was not for a high-throughput automated system. Instead, the focus was on specifying a reliable and safe mezzanine goods lift suited to the day-to-day operational needs of the warehouse.
The client also requested the lift structure be fully clad for aesthetics, ensuring the installation integrated neatly with the appearance of the new warehouse environment.
As with most successful mezzanine lift projects, the solution was driven by use-case clarity rather than headline specification alone.
The key specification points were:
Capacity: 500kg
Travel height: 4156mm to first floor level
Platform size: 1350mm x 1350mm usable platform
Access arrangement: 90-degree loading configuration
Doors and gates: Twin outward-opening interlocked gates at both levels
Enclosure: Full cladding enclosure
Controls: One-touch automatic controls with emergency stop
Floor interface: Bridging plates at ground and upper floor, with no ramp required
This mattered because the project was not simply about raising goods between levels. It was about allowing operators to wheel loads into the lift with minimal friction, while protecting usable warehouse footprint.
During the quotation discussion, Paul also asked practical questions that many serious buyers will recognise:
“How wide are the doors, and would the quote be less if we opted for a mesh, as opposed to fully-enclosed, shaft?”
Those are exactly the right questions, because door width, enclosure type and loading method often affect long-term usability more than buyers initially expect.
In response, it was clarified that the quoted 1350mm x 1350mm platform provided a standard 1350mm door opening, with twin gates opening outwards for ease of loading. This door width formed part of the standard lift configuration and therefore did not increase the overall project cost. The client was also given a choice between a standard mesh enclosure or a fully clad lift structure. While the mesh enclosure formed part of the standard specification, the fully clad option — selected by the client — increased the price slightly but provided a cleaner appearance better suited to the new warehouse environment.
It was also confirmed that bridging plates would provide the transition between the lift and the concrete floor, allowing a no-ramp solution better suited to the building layout.
This is an important lesson for future buyers: platform size alone is not enough. The right mezzanine goods lift has to suit the approach angle, door clearance, loading equipment and available floor space.
The no-ramp arrangement was one of the defining parts of this project.
In many goods lift installations, a ramp can provide a simple way of bridging the platform height. However, in this case the ground floor loading pattern made a ramp impractical. The scissor lift tables carrying aircraft batteries were brought into the warehouse through a nearby personnel door, and a ramp at the lift entrance would have obstructed that route and restricted manoeuvring space.
Because of this layout constraint, the lift needed to allow direct floor-level access without creating an obstruction. The most practical solution was therefore a pit-mounted mezzanine goods lift, allowing the platform to sit flush with the warehouse floor and enabling wheeled equipment to move directly onto the lift.
Paul Greasley’s concern was completely practical, not cosmetic:
“Because the lift tables enter through a personnel door, we needed a solution that allowed direct floor-level access without a ramp getting in the way.”
By installing the lift in a pit and using bridging plates to create a smooth transition between the platform and the floor, the design preserved the access route from the personnel door while maintaining a predictable loading approach for the scissor lift tables. For businesses moving batteries, parts, cages or trolleys to mezzanine level, this type of layout detail often has a greater operational impact than buyers expect at the start of a project.
For mezzanine goods lifts serving multiple levels, the relevant standard is typically BS EN 1570-2:2016. In practical terms, that standard exists to make sure the lift is properly guarded and suitable for use where operators are loading and unloading goods at different levels.
In this installation, the lift included:
Electro-mechanically interlocking gates
Full enclosure
Emergency stop controls
One-touch operation
A configuration intended for indoor, goods-only use by trained operators
These are not optional extras added for brochure value. They are core elements of a correctly specified mezzanine goods lift.
For duty holders, the wider point is suitability. Under PUWER, lifting equipment used at work needs to be appropriate for the task, maintained properly and operated safely. That is why correct specification at the start matters so much. A lift that matches the real load type, loading method and working environment is easier to use, easier to maintain and easier to manage responsibly over time.
The Allaero quotation included delivery and installation, along with pre-delivery inspection (PDI), statutory inspections and operational testing. Estimated installation time was 1–2 days.
That matters because warehouse goods lift projects often succeed or fail on preparation rather than product choice alone. Access for large fabricated components, confirmation of power supply, review of fixing conditions and final drawing approval are all part of a smooth installation process.
For this project, the lift was specified to operate on a 415V 3-phase + neutral supply via a 16A isolator, with the customer providing the isolator and suitable RCD protection. The design also assumed the mast could be supported by the building structure, which is a standard but important point to confirm in mezzanine lift installations.
This is another useful lesson for future buyers: the right goods lift is only part of the solution. Good delivery depends on clear surveys, accurate drawings and practical pre-installation planning.
The installation of the mezzanine goods lift ensured the new warehouse layout could operate as intended from day one. Key benefits included:
Dedicated 500kg mezzanine goods lift providing safe transfer of air parts and aircraft batteries between floors
Predictable loading for wheeled scissor lift tables, allowing operators to move battery loads directly onto the platform
Pit-mounted design with no ramp required, preserving valuable warehouse floor space and maintaining the loading route from the personnel door
Twin interlocked safety gates and full enclosure, improving operator confidence and safe operation
Fully clad lift structure, integrating cleanly with the appearance of the new warehouse environment
Reliable vertical goods movement, allowing the mezzanine floor to function as an effective storage and production area
These are the kinds of outcomes buyers should be looking for when specifying a mezzanine goods lift: not simply vertical movement, but a solution that integrates cleanly with the building layout and supports efficient day-to-day warehouse operations.
No. Whether a ramp is needed depends on the lift design, closed height, floor detail and loading method. In some cases, bridging plates can provide the required transition without taking up the footprint of a permanent ramp.
Yes. Many are designed specifically for trolleys, cages, pump trucks or other wheeled loads. The key is to define the real loading method clearly during the quotation stage.
Both matter, but layout is often underestimated. A lift can have the right capacity and still be awkward if the door width, loading direction or approach route do not match the actual working method.
No. The right choice depends on the environment, the look the customer wants, and how the lift will sit within the building. The key is suitability, not assuming one option is always superior.
Yes. They are often ideal where the lift is operationally important but not used continuously. In those applications, the goal is usually reliability, safe loading and good integration with the building rather than high-cycle automation.
The Allaero project is a strong example of what good mezzanine goods lift specification should look like. The requirement was clear, the operational constraints were understood early, and the final solution matched the way the warehouse would actually function.
This project highlights an important point many buyers overlook at the start: the best goods lift is not necessarily the one with the most impressive specification on paper. It is the one that fits the building layout, preserves valuable space, suits the way loads are handled and works reliably in day-to-day operation.
In this case, Allaero also wanted to avoid introducing forklift truck movements into the new warehouse wherever possible. By installing a dedicated mezzanine goods lift, air parts and aircraft batteries could be transferred safely between floors using wheeled scissor lift tables rather than relying on forklift access within the building.
As Paul Greasley explained during the project,
“We needed to make the best possible use of the available warehouse space.”
That practical constraint helped shape one of the key design decisions — a pit-mounted lift that avoided ramps while maintaining a clear loading route from the personnel door.
For businesses planning similar projects, this installation demonstrates the value of approaching mezzanine goods lift specification as part of the overall warehouse layout rather than treating it as a standalone piece of equipment.
At Scissor Tables UK, we support customers through the entire process — from initial site survey and layout planning through to lift design, manufacture and final installation. Taking this joined-up approach helps ensure the lift integrates properly with the building and provides a reliable solution that supports safe and efficient warehouse operations for years to come.
For buyers researching mezzanine goods lifts, warehouse goods lifts and goods lifts for parts storage or production environments, this installation shows the value of focusing on real use, loading method, access arrangement and footprint rather than treating all goods lifts as interchangeable.
Explore related solutions here: Read more about goods lifts
You can also view other case studies and guides here: Read more about mezzanine goods lifts