Installing a Static Lift Table: What to Plan Before Delivery & Installation

Published on: Friday 20th March 2026

Is Your Site Ready for a Static Lift Table? (Quick Checklist)

Before delivery:

  • 3-phase power supply available at the lift location
  • Access route clear from delivery point to installation area
  • Forklift or suitable equipment available for unloading
  • Installation area clear and prepared
  • Pit constructed correctly if required

Related guides:

On site readiness:

  • Power supply and isolator in place
  • Clear route to final location
  • Enough space to position the lift safely
  • Forklift access if customer is unloading

Most common delays:

  • Power not ready
  • Pit not built correctly
  • Access route blocked
  • No unloading equipment available

Installing a Static Lift Table: What to Plan Before Delivery

Installing a static lift table is usually straightforward.

However, most installation problems do not come from the lift table itself. They usually come from:

  • site preparation
  • access constraints
  • power not being available

This guide explains what should be in place before delivery so installation can proceed without avoidable delays.

Before installation, it can also help to read our static lift table guide to confirm the correct solution has been chosen, and our servicing and maintenance guide to understand long-term ownership requirements.

Installing a static lift table with hydraulic components showing power connection and setup before installation

1. What Actually Goes Wrong on Site

From experience, the most common installation issues are:

  • the lift table cannot be moved through access doors, corridors or working aisles
  • no forklift or unloading equipment is available
  • the installation area is not clear
  • the floor or pit is not level or properly prepared
  • the power supply is not ready
What this means:
Most installation delays are avoidable with basic planning before delivery.

2. Site Preparation Requirements

Before delivery, the site should be ready to receive the lift table.

This typically includes:

  • a clear access route from delivery point to installation area
  • a suitable unloading method, usually a forklift
  • a flat, solid floor or correctly constructed pit
  • sufficient space to position the lift safely

Where the customer is installing the lift themselves, the necessary personnel and equipment should already be arranged before delivery arrives.

What this means:
Even if the specification is correct, installation will be delayed if the lift cannot be moved or positioned once it arrives on site.

3. Delivery, Unloading & Positioning

For standard static lift tables supplied on a supply-only basis:

  • the customer is responsible for unloading and positioning the lift
  • a forklift or equivalent lifting equipment is usually required

For loading bay lifts or other installed solutions:

  • Scissor Tables UK installation teams unload and install the lift
  • the area must still be fully prepared and accessible

Access is critical:

  • door widths and access routes should be checked in advance
  • the delivery point must allow safe unloading
  • the final area must be clear so the lift can be positioned without obstruction

4. Power Supply & Electrical Requirements

Most static lift tables require:

  • 400V 3-phase power supply
  • a suitable isolator, typically 16A where required

Key electrical considerations include:

  • power must be available at the lift table position
  • electrical installation must be carried out by a qualified electrician
  • the incoming voltage must match the lift table requirements

The manuals also make clear that electrical installation and fault tracing should always be performed by qualified electricians, and that the main power switch must be accessible during operation.

Important:
If the power supply is not available at the time of installation, commissioning cannot be completed.

5. Pit Installation Requirements

Where a lift table is pit mounted, the pit must be constructed correctly before installation.

Typical requirements include:

  • pit length = platform length + 30mm
  • pit width = platform width + 30mm
  • pit depth = closed height + 5mm

Additional requirements:

  • the pit must be square and level on all sides
  • the pit floor must be flat and horizontal in all directions
  • the pit floor should be parallel to ground level and mezzanine level where relevant
  • pit edges should include cast-in 50×50 angle irons on all sides
  • service ducting should be provided, minimum 60mm Ø

For remote power packs:

  • duct size should increase to minimum 80mm Ø
  • ducting should be smooth internally
  • ducting should avoid right-angle bends and include a pull cord

If there is a risk of water ingress, drainage must be built into the pit structure.

Your pit detail drawings also reinforce that pit sizing is not approximate. Length and width tolerances, service pipe ducting, and depth all need to match the lift being installed.

Important:
If pit construction guidelines are not followed, the lift may not operate correctly. Any remedial work required during installation for correct operation may be chargeable.

6. Service Hatch for Pit Mounted Lifts

For pit-mounted installations, it is often worth specifying a service hatch within the platform.

This allows:

  • access to hydraulic components
  • easier maintenance and inspection
  • simplified fault finding if the lift stops operating
What this means:
Including a service hatch can avoid the need to remove the lift from the pit during servicing.

7. Positioning & Layout Considerations

The lift table must be positioned to suit how it will be used in practice.

This includes:

  • clear access for forklifts or pallet trucks
  • sufficient space for operators to work safely
  • safe loading and unloading zones

Where goods are moved on and off the lift in the raised position, the manuals advise that the lift should be positioned so loading takes place over the scissor arm attachment area.


8. Installation Responsibilities

Supply only (standard static lift tables):

  • customer unloads and positions the lift
  • customer arranges installation
  • electrical connection is completed by a qualified electrician

Installed solutions (loading bay lifts / customised equipment):

  • Scissor Tables UK carries out installation
  • a pre-delivery inspection (PDI) is carried out beforehand
  • customer must ensure site readiness before installation day

For standard static lift tables supplied only, site visits are not normally carried out in advance. For customised static lift tables and loading bay lifts, drawings are typically provided before manufacture and installation.


9. Commissioning & Testing

Once installed:

  • the lift table should be test run
  • correct motor rotation should be confirmed
  • all safety features should be checked

The lift must:

  • be unloaded during testing
  • be operated with clear visibility of the platform

The operating manuals state that if the motor starts but the table does not lift, two phases should be switched to correct the motor rotation direction.

Common Issue: Motor Runs But Table Does Not Lift

In some cases during commissioning, the motor may run when the UP button is pressed, but the table does not raise.

This is typically caused by:

  • incorrect phase rotation on the power supply

This can occur where:

  • the lift is connected via a commando plug
  • the incoming phases are not aligned correctly

Typical resolution:

  • a qualified electrician swaps two phases in the supply
  • the motor rotation direction is corrected
What this means:
If the motor runs but the lift does not move, the issue is usually electrical rather than mechanical and can often be resolved quickly by checking phase rotation.

10. Common Causes of Delay

  • power supply not installed
  • pit not constructed correctly
  • access route blocked or unsuitable
  • no unloading equipment available
  • installation area not cleared before delivery

11. What a Smooth Installation Looks Like

A straightforward installation typically involves:

  • power supply installed and ready
  • access route clear from the delivery point
  • installation area fully prepared
  • pit constructed correctly where applicable
  • forklift or unloading equipment available where required

If Scissor Tables UK is installing the lift, the site has normally already been reviewed through the PDI process and the area is ready on the agreed date.

What this means:
When access, power and the installation area are all ready before delivery, installation is usually straightforward and without issue.